The Projected column shows the projected total amount that will be spent for that Expense Category based upon Spent to Date & % Complete.
Formula
Projected = Spent to Date / % Complete
Ex: 5,000 / 50% = $10,000 Projected
The Projected column shows the projected total amount that will be spent for that Expense Category based upon Spent to Date & % Complete.
Formula
Projected = Spent to Date / % Complete
Ex: 5,000 / 50% = $10,000 Projected