What is the % Complete Column on the Project Budgeter?

Updated over a year ago

The % Complete Column is the estimated amount you have completed for a Category.

The % Complete is used to calculate the Projected Final Costs for that Category, which is ultimately compared to your Budgeted Amount.

Projected Formula

Projected = Spent to Date / % Complete

Variance = Projected - Budgeted

Example

Ex: Let's say you had an initial budget of $4,000 for roofing. There was a change order and the roofing ended up costing $4,500.

Projected = $4,500 / 100%

= $4,500

Variance = $4,500 - $4,000

= +$500 over budget